NEW QUESTION # 47
What needs to be activated as a prerequisite for using a product allocation check? Note: There are 2 correct answers to this question.

  • A. The availability check against product allocation in Sales and Distribution
  • B. The availability check against product allocation for basic Available-to-Promise
  • C. The availability check against product allocation in the context of aATP
  • D. The availability check against product allocation per client

Answer: C,D


NEW QUESTION # 48
What are some characteristics of the supplier consignment stock? Note: There are 3 correct answers to this question.

  • A. Consignment stock belongs to your valuated inventory
  • B. Consignment stock is managed specific to supplier at the storage location level
  • C. Blocked consignment stock can be transferred to your own stock
  • D. Unrestricted-use consignment stock is available for planning
  • E. Consignment stock is owned by the supplier

Answer: B,D,E


NEW QUESTION # 49
Which of the following key features does the Stock - Single Material app provide? Note: There are 2 correct answers to this question.

  • A. Indicate if the selected material is a slow-moving material
  • B. Display the stock history for each plant or storage location for the last 11 periods
  • C. Display the stock of a material by plant, by storage location, and by bin location
  • D. Compare the stock with the safety stock value defined for the material

Answer: B,D


NEW QUESTION # 50
You procure some materials exclusively via subcontracting. You want Material Requirements Planning (MRP) to create subcontract purchase requisitions for these materials instead of normal purchase requisitions. What must you do for each of these materials? Note: There are 2 correct answers to this question.

  • A. Create a routing with an operation to be processed externally
  • B. Set a special procurement type for subcontracting in the material master record
  • C. Create a bill of material with the components to be provided
  • D. Set a special MRP group for subcontracting in the material master record

Answer: B,C


NEW QUESTION # 51
How can business users create new analytics content? Note: There are 3 correct answers to this question.

  • A. Change underlying database tables of standard data sources
  • B. Combine current and historical data
  • C. Change existing data sources by adding filters
  • D. Create new data sources via joins of standard data sources
  • E. Create additional key figures in existing data sources

Answer: A,D,E


NEW QUESTION # 52
Which document do you use to initiate a supplier return process?

  • A. A stock transport order
  • B. A return delivery
  • C. A return purchase order
  • D. A return sales order

Answer: C


NEW QUESTION # 53
You want to implement cycle counting for some materials in your warehouse. Which settings are required? Note: There are 2 correct answers to this question.

  • A. Configure cycle counting indicators
  • B. Maintain counting dates
  • C. Assign a cycle counting indicator to the relevant materials
  • D. Assign a cycle counting indicator to the relevant storage location

Answer: A,C


NEW QUESTION # 54
The Automotive Supply to Customer - Inventory Management (55F) scope item describes an end- to-end process for automotive suppliers. Which of the following options does this scope item include to streamline and accelerate the process? Note: There are 3 correct answers to this question.

  • A. Invoicing Plan
  • B. Purchase Contract
  • C. Self-Billing
  • D. Evaluated Receipt Settlement (ERS)
  • E. Purchase Scheduling Agreement

Answer: C,D,E


NEW QUESTION # 55
Which of the following capabilities does backorder processing in basic ATP offer? Note: There are 2 correct answers to this question.

  • A. Schedule jobs to automatically reprioritize and reschedule sales and stock transport orders
  • B. Maintain email templates and automatically inform customers about backorders
  • C. Maintain rules for automatic rescheduling and redistribution of materials with limited availability
  • D. Schedule jobs that automatically set the deletion flag on backorder items

Answer: A,C


NEW QUESTION # 56
You want to create a purchase order for subcontracting. What must you do? Note: There are 2 correct answers to this question.

  • A. In the purchase order item, enter the special stock indicator
  • B. Choose the appropriate item category
  • C. In the purchase order item, enter the components to be provided
  • D. Choose the appropriate purchase order type

Answer: A,B


NEW QUESTION # 57
In what phase of the SAP Activate methodology do you test the business processes?

  • A. Explore
  • B. Prepare
  • C. Realize
  • D. Deploy

Answer: C


NEW QUESTION # 58
What can you use the Query Browser app to do? Note: There are 2 correct answers to this question.

  • A. Modify an SAP-created analytical query
  • B. Create and publish a query
  • C. Create your own tags for CDS views
  • D. View authorized published queries

Answer: C,D


NEW QUESTION # 59
Which price is used to valuate a cross-plant stock transfer posting?

  • A. The mean value of the material's valuation prices in issuing and receiving plants
  • B. The price that the user must enter when posting the stock transfer
  • C. The valuation price of the material in the issuing plant
  • D. The valuation price of the material in the receiving plant

Answer: C


NEW QUESTION # 60
What determines the set of data migration objects available from the Migrate Your Data application?

  • A. The selected target fields
  • B. The selected business scenarios
  • C. The customer legacy system
  • D. The selected source system

Answer: B


NEW QUESTION # 61
How can shipped stock be monitored in the Cross-Plant Transfer Posting (1P7) scope item?

  • A. As blocked stock without plant assignment
  • B. As blocked stock in the delivering plant
  • C. As transfer stock in the delivering plant
  • D. As transfer stock in the receiving plant

Answer: D


NEW QUESTION # 62
Which of the following is a prerequisite for using Automated Receipt Settlement (ERS) in a procurement process? Note: There are 2 correct answers to this question.

  • A. The indicator for ERS is set in the purchase order item.
  • B. The indicator for ERS is set in the purchasing info record.
  • C. The indicator for ERS is set in the material master record.
  • D. The indicator for ERS is set in the supplier master record.

Answer: A,D


NEW QUESTION # 63
Which of the following business areas are part of the Line of Business Supply Chain, but are covered in separate courses? Note: There are 2 correct answers to this question.

  • A. Inventory Management
  • B. Warehouse Management
  • C. Advanced Order Promising
  • D. Transportation Management

Answer: B,D


NEW QUESTION # 64
What are key activities of the Prepare phase of the SAP Activate methodology? Note: There are 3 correct answers to this question.

  • A. Starter system provisioning
  • B. Project setup
  • C. Customer self-enablement
  • D. User training
  • E. Data migration

Answer: A,B,C


NEW QUESTION # 65
In a subcontracting process, in which process step does the consumption posting of the components take place?

  • A. Stock transfer to subcontracting stock
  • B. Creation of subcontracting purchase order
  • C. Goods receipt for subcontracting purchase order
  • D. Invoice receipt for subcontracting purchase order

Answer: C


NEW QUESTION # 66
......